As reported, we received the required permits for the construction work on site several days before the Corona Virus restrictions forced us to stop for 2 months. Since the beginning of May, the work on site is progressing in a rapid rate – We are now working on the ground level, we have completed the building of foundations, and are now casting an underground elevator shaft and ground floor plumbing. The builders are connecting all the iron for of the ground columns that will become the ground floor.
The work on site continues at a good rate, to complete the construction by the end of 2020 as planned and enable us to open the first two pre-school classes for the children by winter/spring of 2021.

             